There’s a few things you can do when undertaking your data refresh into a non-production environment one of them is modifying your batch jobs to ‘Withhold’ status ensuring they won’t start to run when you after you start up your AOS’s and then configure your batch server settings. After the script has been ran you can set the status of jobs you want to run back to ‘Waiting’ status at a later point during the data refresh process, happy in the knowledge that you know no batch jobs are going to start emailing customers or update/talk to other external systems.
SQL Script:
-- Change to correct DB USE <Your Ax Database> -- Set all Batch Jobs to Withhold status UPDATE BatchJob SET status = 0
You could also have a scenario where only certain batch jobs should be set to Withhold status, you could do this by adding the batch jobs you want to continue to run into a table and then only update the ones not in that table to Withhold. An example script to do this can be found below:
Pre-Requisites: Create a table with one data field called ‘Caption’, populate table with batch job names that you want to continue to run in your non-production environment (e.g. not be at withhold status)
SQL Script:
-- Change to correct DB USE <Your Ax Database> UPDATE BatchJob SET status = 0 WHERE Caption NOT IN (SELECT Caption FROM <the table name created in pre-requisites>)
Disclaimer: Ensure any batch jobs you add to this table don’t have other parameters that need to be changed prior to them running again in the non-production environment.